Project Controls in the AI EraReporting, dashboards and data foundations · Lesson 17 of 22

Reports and dashboards that drive decisions

Article · 13 min · 8 min lecture

Video lecture

Reports and dashboards that drive decisions

9 chapters · about 8 min · full transcript

Coming soon

Chapter 1 of 9

Twenty pages nobody reads

  • Start from the decision
  • The one-page executive summary
  • RAG rules and dashboards that show trends

The narrated lecture is in production

Every chapter is scripted and ready. Browse the chapters and read the full transcript now — the video will appear here when it’s published.

Chapters

Start from the decision

A report is a product with customers. Before designing it, ask: who reads this, what decisions do they make, and what do they need to know to make them? A sponsor needs a different view from a site manager.

AudienceKey decisionsWhat they need
Board / sponsorFunding, scope, risk appetite, escalationsForecast vs approved, confidence range, top risks, decisions required
Project directorResource allocation, recovery plansControl-account performance, trends, critical path, change pipeline
Control account managerDaily/weekly work prioritiesDetailed variances, look-ahead, constraints
ClientAcceptance, change approvalsProgress, milestones, change status, issues needing client action

The one-page executive summary

PROJECT: ______   Period: ______   Overall status: [G / A / R with definition]
1. Headline (2–3 sentences): what changed and why it matters
2. Forecast: EAC ____ vs BAC ____ (+/- __%) | Finish ____ vs baseline ____ | P80 ____
3. Performance: CPI ____ (trend) | SPI(t) ____ (trend) | Contingency remaining ____
4. Top 3 variances: cause – impact – action – owner
5. Top 3 risks: change since last period – response
6. Decisions required from you: ______ by ______

"Decisions required" is the most important section and the most often omitted.

RAG status with rules

RAG ratings are useful only if defined. Illustrative rule set:

StatusRule
GreenEAC within BAC; forecast finish within baseline; no unmitigated high risks
AmberEAC within BAC + contingency, or forecast slip ≤ 4 weeks, recovery plan in place
RedEAC exceeds BAC + contingency, or slip > 4 weeks, or no credible recovery plan

Without rules, people report "green" until it becomes impossible, producing the famous "watermelon" project: green outside, red inside.

Dashboard design principles

  • Show trends, not snapshots. A CPI line over 12 periods beats a single gauge.
  • Compare with something. Actual vs baseline, forecast vs approved, this period vs last.
  • Use the right chart. S-curves for cumulative PV/EV/AC; bar charts for variance by control account; line charts for indices; tables for top risks.
  • Keep it sparse. A few metrics that matter, with the ability to drill down.
  • Explain. Every chart needs a sentence saying what it means.
  • Timestamp and source. Show data date and data source on every page.

The EVM S-curve chart

Plot cumulative PV (baseline), EV and AC over time, and extend the forecast (EAC) to completion. The gap between EV and PV shows schedule position in money; the gap between EV and AC shows cost efficiency. Add the BAC line and EAC point.

Worked example

Illustrative. A fictional telecoms operator in Pakistan ran 30 tower-upgrade projects with 20-page reports each. Executives read none of them. The PMO replaced them with a portfolio dashboard: a scatter of CPI vs SPI(t) for all projects, a table of the ten worst EAC movements, and a one-page summary for any project in red. Review meetings shortened and focused on the handful of projects needing decisions.

Narrative writing

Numbers need words. A strong narrative:

  1. States the headline first.
  2. Explains the cause, not only the symptom.
  3. Quantifies impact on cost, schedule and risk.
  4. Describes actions with owners and dates.
  5. Asks explicitly for decisions.

Common mistakes

  • Reports designed around available data rather than decisions.
  • Undefined RAG status.
  • Dozens of KPIs with no prioritisation.
  • No data date, so readers do not know how current it is.
  • Charts without interpretation.

AI in reporting

Generative AI can draft narratives from structured data in seconds. Use it to create a first draft, then have the controls lead verify every number against the source, check causes with the owners and add judgment. Label AI-assisted content according to your organisation's policy.

Quick self-check

Hand your latest report to a colleague who does not know the project and give them two minutes. Ask them to tell you the forecast, the main problem and what decision is needed. If they cannot, the report is not doing its job, however accurate the numbers are. Rewrite the headline and the decisions section first; those two parts do most of the work.

Hands-on: RAG by formula, not by feeling

Named inputs: EAC, BAC, Contingency_remaining, Slip_weeks, Recovery_plan (Y/N), Unmitigated_high_risks (count)
RAG =IFS(
      OR(EAC>BAC+Contingency_remaining, Slip_weeks>4, AND(Slip_weeks>0, Recovery_plan="N")), "Red",
      OR(EAC>BAC, Slip_weeks>0, Unmitigated_high_risks>0), "Amber",
      TRUE, "Green")

Publish the rule on the report itself so readers know what each colour means. Thresholds are illustrative; set your own in the project's controls plan.

Hands-on: two core visuals in Power BI (or Excel)

Model: one table EVM with Period, Account, PV, EV, AC (cumulative) and a DataDate table.

DAX measures
PV Cum   = SUM ( EVM[PV] )
EV Cum   = SUM ( EVM[EV] )
AC Cum   = SUM ( EVM[AC] )
CPI      = DIVIDE ( [EV Cum], [AC Cum] )
SPI      = DIVIDE ( [EV Cum], [PV Cum] )

Visual 1: line chart, axis Period, values PV Cum, EV Cum, AC Cum, plus a constant line at BAC. Visual 2: line chart of CPI by Period with a constant line at 0.95. Add a card showing the data date. In Excel, the same visuals come from a pivot table and a line chart.

Prompt template: executive narrative (approved enterprise AI tool)

Role: project controls analyst. Write a 120–150 word executive headline for the one-page summary.
Use ONLY the table provided. Structure: (1) headline, (2) cost forecast with range, (3) schedule forecast,
(4) main driver, (5) decisions required with dates. Cite the table column for each figure in brackets.
If a cause is not in the table, write "cause to be confirmed". Use British English; no adjectives like "significant"
unless a threshold is stated.

Tools such as Microsoft 365 Copilot, ChatGPT Enterprise or Claude can run this template if your organisation has approved them; the controls lead verifies every number and approves the text.

How to measure success

  • The two-minute test passes with a reader outside the project.
  • Every report carries a data date, a source and a decisions-required section.
  • Time from data date to report issue (target falling without loss of accuracy).

Key takeaways

  • Design reports around audiences and the decisions they make.
  • The executive summary must include forecasts, confidence, top variances and risks, and decisions required.
  • Define RAG rules to avoid 'watermelon' reporting.
  • Dashboards show trends and comparisons, cite the data date and explain each chart.

Check your understanding

Quick questions to lock in the lesson. They don’t count towards your certificate.

  1. What is the most commonly omitted but most important section of an executive project report?
  2. A project reports green for months, then suddenly red. Which fix most directly addresses this?
  3. Which chart best shows cumulative planned value, earned value and actual cost over time?

Put it into practice

Redesign a report you receive or produce into the one-page executive template. Add a 'decisions required' section and objective RAG rules.

Enrol for free to save your progress

Reading is always free. Enrol to keep your place, take the final assessment and earn a verifiable certificate.